

Project: Carolina Beach Road Improvements (U-5790) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2029 |
This project will widen US421/Carolina Beach Road from NC132/College Road to Sanders Road and includes intersection improvements at US421/Carolina Beach Road & NC132/College Road. |
|
Project Files: Public Meeting Map |
Project: Carolina Beach Road Streetscape (U-5729) Project Type: Roadway Projects |
Status: Construction Delayed until FY2029 |
This project will upgrade US421/Carolina Beach Road from US421/Burnett Boulevard to US117/Shipyard Boulevard. |
|
Project Files: Public Workshop Map |
Project: Castle Hayne Road Widening (U-5863) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2025 |
This project will widen Castle Hayne Road from I-140/Wilmington Bypass to Division Drive. |
|
Project Files: Alternative 1 Map 1 Alternative 1 Map 2 Alternative 1 Map 3 Alternative 3 Map 1 Alternative 3 Map 2 Alternative 3 Map 3 |
Project: College Road & Martin Luther King Jr. Parkway Interchange (U-5792) Project Type: Roadway Projects |
Status: Anticipated ROW FY2024, Construction FY2026 |
This project will construct an interchange at US117/College Road & US74/Martin Luther King Jr. Parkway. |
|
Project Files: Public Workshop Map |
Project: College Road Access Management & Travel Time Improvements (U-5702A) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2024 |
This project includes access management and travel time improvements along NC132/College Road between New Centre Drive and US117/Shipyard Boulevard. |
Project: College Road Access Management & Travel Time Improvements (U-5702B) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2025 |
This project includes access management and travel time improvements along NC132/College Road between US117/Shipyard Boulevard and US421/Carolina Beach Road. |
Project: College Road Improvements (U-5704) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2029 |
This project will install access management and travel time savings improvements on College Road from Wilshire Boulevard to US117/Shipyard Boulevard and includes an interchange at US76/Oleander Drive. |
|
Project Files: Public Meeting Map |
Project: College Road Improvements (U-5881) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2029 |
This project will upgrade NC132/College Road between Gordon Road and New Centre Drive. |
Project: Eastwood Road & Military Cutoff Road Intersection Improvements (U-5710) Project Type: Roadway Projects |
Status: ROW in Progress, Anticipated Let Date FY2022 |
This project will increase capacity and mobility at US74/Eastwood Road & Military Cutoff Road. |
|
Project Files: Public Hearing Map |
Project: Gordon Road Widening (U-6202) Project Type: Roadway Projects |
Status: Anticipated ROW FY2022, Construction FY2024 |
This project will widen Gordon Road to four lanes between US17 BUS/Market Street and I-40. |
Project: Hampstead Bypass (R-3300) Project Type: Roadway Projects |
Status: Planning and Design in Progress, ROW in Progress |
This project will construct a multi-lane facility on new location as an alternate and parallel route to US17 between Porters Neck and north of Hampstead. The first section (R-3300A) would extend from the US17 Wilmington Bypass to NC210. The anticipated let date for this section is FY2027. The second section (R-3300B) would extend from NC210 to north of Hampstead. The anticipated let date for this section is FY2022. For more information, please visit NCDOT’S project page here. |
|
Project Files: Official Adopted Corridor Map Final Compiled Maps |
Project: Independence Boulevard Extension (U-4434) Project Type: Roadway Projects |
Status: Anticipated ROW FY2024, Construction FY2028 |
This project will construct a roadway on new location from Randall Parkway to US74/Martin Luther King Jr. Parkway. For more information, please visit NCDOT’s project page here. |
|
Project Files: Project Area Map Study Area Map 1 Study Area Map 2 |
Project: Isabelle Holmes Bridge Flyovers (U-5731) Project Type: Roadway Projects |
Status: Anticipated ROW FY2024, Construction FY2028 |
This project will construct an interchange at US421 & the Isabelle Holmes Bridge on Eagle Island. |
|
Project Files: Vicinity Map |
Project: Kerr Avenue & Martin Luther King Jr. Parkway Interchange (U-3338C) Project Type: Roadway Projects |
Status: ROW in Progress, Construction Delayed until FY2029 |
This project will construct an interchange at Kerr Avenue & US74/Martin Luther King Jr. Parkway. |
Project: Kerr Avenue Extension (U-6201) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2028 |
This project will extend Kerr Avenue from Wrightsville Avenue to US76/Oleander Drive. |
Project: Market Street Access Management Improvements: Phase II (U-4902B) Project Type: Roadway Projects |
Status: ROW in Progress, Construction Delayed until FY2029 |
This project will install a median along US17 BUS/Market Street from CSX Railroad to Cinema Drive and from Jacksonville Street to north of US117/NC132/College Road. |
|
Project Files: Design - Public Meeting Map Project Location Map |
Project: Market Street Access Management Improvements: Phase III (U-4902C) Project Type: Roadway Projects |
Status: ROW in Progress, Construction Delayed until FY2029 |
This project will install access management improvements on US17 BUS/Market Street from north of US117/NC132/College Road to Station Road and includes an interchange at Market Street & Eastwood Road. |
|
Project Files: Design - Public Meeting Map - Sheet 1 (Market Street & Eastwood Road Interchange) Design - Public Meeting Map - Sheet 2 (Access Management Improvements) |
Project: Market Street Access Management Improvements: Phase IV (U-4902D) Project Type: Roadway Projects |
Status: Under Construction, 48.45% Complete |
This project will install a median along US17 BUS/Market Street from Middle Sound Loop Road to Mendenhall Drive/Marsh Oaks Drive. |
|
Project Files: Project Location Map |
Project: Military Cutoff Road Extension (U-4751) Project Type: Roadway Projects |
Status: Under Construction, 57.16% Complete |
This project will extend Military Cutoff Road north from its current terminus at US17 BUS/Market Street to the US17 Wilmington Bypass. For more information, please visit NCDOT’s project page here. |
|
Project Files: 2011 Revised Corridor Map Design Public Meeting Map Detail Public Meeting Map |
Project: NC133 at 23rd Street Roundabout (U-5954) Project Type: Roadway Projects |
Status: Anticipated ROW FY2025, Construction FY2027 |
This project will construct a roundabout at NC133/Castle Hayne Road and N. 23rd Street. |
Project: NC133 Roadway Modernization (U-5914) Project Type: Roadway Projects |
Status: ROW in Progress, Anticipated Let Date FY2022 |
This project will modernize NC133/River Road SE from US17/74/76 to Old River Road. |
Project: New Route from 23rd Street to 26th Street (U-5926) Project Type: Roadway Projects |
Status: Anticipated Let Date FY2024 |
This project will construct a roadway on new location from 23rd Street to 26th Street. |
Project: Oleander Drive & Greenville Loop Road/Greenville Avenue Intersection Upgrade (U-6128) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2029 |
This project includes dual lefts at the intersection of US76/Oleander Drive and Greenville Loop Road/Greenville Avenue. |
Project: South Front Street Widening (U-5734) Project Type: Roadway Projects |
Status: Preliminary Engineering |
This project will widen US421/Front Street from the Cape Fear Memorial Bridge to US421/Carolina Beach Road. |
Project: US17 Superstreet (U-5732) Project Type: Roadway Projects |
Status: ROW in Progress |
This project will install a median and intersection modifications along US17 in Hampstead between Washington Acres Road and Sloop Point Loop Road. Construction will begin following the completion of the Hampstead Bypass. |
Project: Wilmington Citywide Signal System Upgrade (U-6199) Project Type: Roadway Projects |
Status: Construction Delayed, Anticipated ROW FY2028 |
This project will upgrade the City of Wilmington’s citywide signal system. |
Project: City of Wilmington Traffic Signal Preemption – Phase II (U-6235) Project Type: Roadway Projects |
Status: Design |
This project will install traffic preemption equipment at an additional 50 locations throughout the City of Wilmington and GPS devices on fire apparatus. |
Project: City of Wilmington Traffic Signal Preemption -Phase I (U-5534T) Project Type: Roadway Projects |
Status: Complete |
This project installed traffic preemption equipment at 27 locations throughout the City of Wilmington and GPS devices on fire apparatus. |
Project: US421 & Hamlet Avenue Traffic Signal and Pedestrian Improvements (U-6233) Project Type: Roadway Projects |
Status: On Hold |
This project includes the installation of a new traffic signal and improvements to pedestrian accommodations at the intersection of US421 (Lake Park Boulevard) and Hamlet Avenue in Carolina Beach. |
Project: Wrightsville Ave/Greenville Ave Intersection Improvements (U-5534C) Project Type: Roadway Projects |
Status: Design, Anticipated ROW FY2022 |
The project consists of the construction of intersection re-alignment improvements at Wrightsville Avenue/Greenville Avenue including bike lanes and sidewalks along Greenville Avenue from Wrightsville Avenue to Hinton Avenue. |
|
Project Files: Wrightsville Ave/Greenville Ave Map |
Project: 2014 Transportation Bond Initiative Project Type: Roadway Projects |
Status: See Link Below |
Project: City of Wilmington’s 5-Year Improvement Plan Project Type: Roadway Projects |
Status: See Link Below |